Your browser does not support the video tag. McLaren Grand Ledge: January 2025 Update Construction on the new ambulatory care center and freestanding emergency department continues to progress, even through the cold temperatures and falling snow. Here are a few of the milestones accomplished during this month: Prefabrication wall panels began being placed in mid-January The roof decking is completed along the entire building Plans to install temporary enclosures for doors and windows will begin shortly As we move into February, we’re excited to continue to see progress with plans to start prepping the east end of the building and the roofing system. Follow along and view the live progress through our construction cam: Live Construction Cam