McLaren Grand Ledge: March 2025 Update

The weather is beginning to turn over to spring just in time for our building to receive a facelift outside with brickwork starting this week. Meanwhile, a lot has progressed in the interior of the building:

  • Wall framing in the emergency department area is currently being worked on
  • Drywall will be following the completion of framing
  • The concrete flooring is now completed
  • Wall layout of the entire building is 100% complete